221 Service Outage Saturday 5/18 10am-2pm rolling
We will be replacing network hardware, which will affect the server infrastructure MCS has in 221 on Saturday 5/18 between 10am and 2pm. What needs to be done ahead of time to prepare for this? Corby Schmitz Sent from my mobile office
I don't think there is much that we can do, we're going to have to take this outage. Is the 4k going to reboot, or is it something upstream that is being worked on? ---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055 ----- Original Message ----- From: "Corby Schmitz" <[email protected]> To: [email protected] Sent: Friday, May 11, 2012 1:40:35 PM Subject: 221 Service Outage Saturday 5/18 10am-2pm rolling We will be replacing network hardware, which will affect the server infrastructure MCS has in 221 on Saturday 5/18 between 10am and 2pm. What needs to be done ahead of time to prepare for this? Corby Schmitz Sent from my mobile office
We are replacing the 4k and its oversubscribed hardware to line rate fex shelves and the new 7K in 221. Corby Schmitz Sent from my mobile office On May 11, 2012, at 13:45, Dan Olson <[email protected]> wrote:
I don't think there is much that we can do, we're going to have to take this outage. Is the 4k going to reboot, or is it something upstream that is being worked on?
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby Schmitz" <[email protected]> To: [email protected] Sent: Friday, May 11, 2012 1:40:35 PM Subject: 221 Service Outage Saturday 5/18 10am-2pm rolling
We will be replacing network hardware, which will affect the server infrastructure MCS has in 221 on Saturday 5/18 between 10am and 2pm. What needs to be done ahead of time to prepare for this?
Corby Schmitz Sent from my mobile office
What will the length of the outage be for each host? -- Craig On May 11, 2012, at 1:52 PM, Corby Schmitz wrote:
We are replacing the 4k and its oversubscribed hardware to line rate fex shelves and the new 7K in 221.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 13:45, Dan Olson <[email protected]> wrote:
I don't think there is much that we can do, we're going to have to take this outage. Is the 4k going to reboot, or is it something upstream that is being worked on?
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby Schmitz" <[email protected]> To: [email protected] Sent: Friday, May 11, 2012 1:40:35 PM Subject: 221 Service Outage Saturday 5/18 10am-2pm rolling
We will be replacing network hardware, which will affect the server infrastructure MCS has in 221 on Saturday 5/18 between 10am and 2pm. What needs to be done ahead of time to prepare for this?
Corby Schmitz Sent from my mobile office
60 seconds or less is the expected outage per-host. Corby Schmitz Sent from my mobile office On May 11, 2012, at 14:17, Craig Stacey <[email protected]> wrote:
What will the length of the outage be for each host? -- Craig
On May 11, 2012, at 1:52 PM, Corby Schmitz wrote:
We are replacing the 4k and its oversubscribed hardware to line rate fex shelves and the new 7K in 221.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 13:45, Dan Olson <[email protected]> wrote:
I don't think there is much that we can do, we're going to have to take this outage. Is the 4k going to reboot, or is it something upstream that is being worked on?
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby Schmitz" <[email protected]> To: [email protected] Sent: Friday, May 11, 2012 1:40:35 PM Subject: 221 Service Outage Saturday 5/18 10am-2pm rolling
We will be replacing network hardware, which will affect the server infrastructure MCS has in 221 on Saturday 5/18 between 10am and 2pm. What needs to be done ahead of time to prepare for this?
Corby Schmitz Sent from my mobile office
Okay, cool. I see no issue with this. -- Craig On May 11, 2012, at 2:30 PM, Corby Schmitz wrote:
60 seconds or less is the expected outage per-host.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 14:17, Craig Stacey <[email protected]> wrote:
What will the length of the outage be for each host? -- Craig
On May 11, 2012, at 1:52 PM, Corby Schmitz wrote:
We are replacing the 4k and its oversubscribed hardware to line rate fex shelves and the new 7K in 221.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 13:45, Dan Olson <[email protected]> wrote:
I don't think there is much that we can do, we're going to have to take this outage. Is the 4k going to reboot, or is it something upstream that is being worked on?
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby Schmitz" <[email protected]> To: [email protected] Sent: Friday, May 11, 2012 1:40:35 PM Subject: 221 Service Outage Saturday 5/18 10am-2pm rolling
We will be replacing network hardware, which will affect the server infrastructure MCS has in 221 on Saturday 5/18 between 10am and 2pm. What needs to be done ahead of time to prepare for this?
Corby Schmitz Sent from my mobile office
Also, I presume you mean 5/19. -- Craig On May 11, 2012, at 2:35 PM, Craig Stacey wrote:
Okay, cool. I see no issue with this. -- Craig
On May 11, 2012, at 2:30 PM, Corby Schmitz wrote:
60 seconds or less is the expected outage per-host.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 14:17, Craig Stacey <[email protected]> wrote:
What will the length of the outage be for each host? -- Craig
On May 11, 2012, at 1:52 PM, Corby Schmitz wrote:
We are replacing the 4k and its oversubscribed hardware to line rate fex shelves and the new 7K in 221.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 13:45, Dan Olson <[email protected]> wrote:
I don't think there is much that we can do, we're going to have to take this outage. Is the 4k going to reboot, or is it something upstream that is being worked on?
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby Schmitz" <[email protected]> To: [email protected] Sent: Friday, May 11, 2012 1:40:35 PM Subject: 221 Service Outage Saturday 5/18 10am-2pm rolling
We will be replacing network hardware, which will affect the server infrastructure MCS has in 221 on Saturday 5/18 between 10am and 2pm. What needs to be done ahead of time to prepare for this?
Corby Schmitz Sent from my mobile office
Yes, I got confused on the dates. It is Saturday 5/19. -- corby On 5/11/12 2:36 PM, "Stacey, Craig J." <[email protected]> wrote:
Also, I presume you mean 5/19. -- Craig
On May 11, 2012, at 2:35 PM, Craig Stacey wrote:
Okay, cool. I see no issue with this. -- Craig
On May 11, 2012, at 2:30 PM, Corby Schmitz wrote:
60 seconds or less is the expected outage per-host.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 14:17, Craig Stacey <[email protected]> wrote:
What will the length of the outage be for each host? -- Craig
On May 11, 2012, at 1:52 PM, Corby Schmitz wrote:
We are replacing the 4k and its oversubscribed hardware to line rate fex shelves and the new 7K in 221.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 13:45, Dan Olson <[email protected]> wrote:
I don't think there is much that we can do, we're going to have to take this outage. Is the 4k going to reboot, or is it something upstream that is being worked on?
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby Schmitz" <[email protected]> To: [email protected] Sent: Friday, May 11, 2012 1:40:35 PM Subject: 221 Service Outage Saturday 5/18 10am-2pm rolling
We will be replacing network hardware, which will affect the server infrastructure MCS has in 221 on Saturday 5/18 between 10am and 2pm. What needs to be done ahead of time to prepare for this?
Corby Schmitz Sent from my mobile office
I'll also be onsite doing other work that day, so I can help troubleshoot issues if they arise. I would like to do the load balancers two connections last. 6 net load balancer address is 00:25:90:03:EB:81 15 net load balancer address is 00:25:90:03:EB:80 ---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055 ----- Original Message ----- From: "Corby B. Schmitz" <[email protected]> To: "Craig J. Stacey" <[email protected]>, "Corby Schmitz" <[email protected]> Cc: "Daniel E. Olson" <[email protected]>, [email protected] Sent: Friday, May 11, 2012 2:44:54 PM Subject: Re: 221 Service Outage Saturday 5/18 10am-2pm rolling Yes, I got confused on the dates. It is Saturday 5/19. -- corby On 5/11/12 2:36 PM, "Stacey, Craig J." <[email protected]> wrote:
Also, I presume you mean 5/19. -- Craig
On May 11, 2012, at 2:35 PM, Craig Stacey wrote:
Okay, cool. I see no issue with this. -- Craig
On May 11, 2012, at 2:30 PM, Corby Schmitz wrote:
60 seconds or less is the expected outage per-host.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 14:17, Craig Stacey <[email protected]> wrote:
What will the length of the outage be for each host? -- Craig
On May 11, 2012, at 1:52 PM, Corby Schmitz wrote:
We are replacing the 4k and its oversubscribed hardware to line rate fex shelves and the new 7K in 221.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 13:45, Dan Olson <[email protected]> wrote:
I don't think there is much that we can do, we're going to have to take this outage. Is the 4k going to reboot, or is it something upstream that is being worked on?
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby Schmitz" <[email protected]> To: [email protected] Sent: Friday, May 11, 2012 1:40:35 PM Subject: 221 Service Outage Saturday 5/18 10am-2pm rolling
We will be replacing network hardware, which will affect the server infrastructure MCS has in 221 on Saturday 5/18 between 10am and 2pm. What needs to be done ahead of time to prepare for this?
Corby Schmitz Sent from my mobile office
i am copying the engineer leading the work so he can make arrangements. Corby Schmitz Sent from my mobile office On May 11, 2012, at 14:51, "Dan Olson" <[email protected]> wrote:
I'll also be onsite doing other work that day, so I can help troubleshoot issues if they arise. I would like to do the load balancers two connections last. 6 net load balancer address is 00:25:90:03:EB:81 15 net load balancer address is 00:25:90:03:EB:80
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby B. Schmitz" <[email protected]> To: "Craig J. Stacey" <[email protected]>, "Corby Schmitz" <[email protected]> Cc: "Daniel E. Olson" <[email protected]>, [email protected] Sent: Friday, May 11, 2012 2:44:54 PM Subject: Re: 221 Service Outage Saturday 5/18 10am-2pm rolling
Yes, I got confused on the dates. It is Saturday 5/19.
-- corby
On 5/11/12 2:36 PM, "Stacey, Craig J." <[email protected]> wrote:
Also, I presume you mean 5/19. -- Craig
On May 11, 2012, at 2:35 PM, Craig Stacey wrote:
Okay, cool. I see no issue with this. -- Craig
On May 11, 2012, at 2:30 PM, Corby Schmitz wrote:
60 seconds or less is the expected outage per-host.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 14:17, Craig Stacey <[email protected]> wrote:
What will the length of the outage be for each host? -- Craig
On May 11, 2012, at 1:52 PM, Corby Schmitz wrote:
We are replacing the 4k and its oversubscribed hardware to line rate fex shelves and the new 7K in 221.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 13:45, Dan Olson <[email protected]> wrote:
I don't think there is much that we can do, we're going to have to take this outage. Is the 4k going to reboot, or is it something upstream that is being worked on?
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby Schmitz" <[email protected]> To: [email protected] Sent: Friday, May 11, 2012 1:40:35 PM Subject: 221 Service Outage Saturday 5/18 10am-2pm rolling
We will be replacing network hardware, which will affect the server infrastructure MCS has in 221 on Saturday 5/18 between 10am and 2pm. What needs to be done ahead of time to prepare for this?
Corby Schmitz Sent from my mobile office
Dan, I've got the ports for your load balancers marked and will save those for last, I should be ready to move them around 11:00 on Saturday. We could also move them before Saturday if you wanted, the new equipment is already in place and ready to go. Brandon -- Brandon Siegel Jr. Network Engineer Computing and Information Systems Argonne National Laboratory [email protected] (630)252-0261 On 5/11/12 6:00 PM, "Schmitz, Corby B." <[email protected]> wrote:
i am copying the engineer leading the work so he can make arrangements.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 14:51, "Dan Olson" <[email protected]> wrote:
I'll also be onsite doing other work that day, so I can help troubleshoot issues if they arise. I would like to do the load balancers two connections last. 6 net load balancer address is 00:25:90:03:EB:81 15 net load balancer address is 00:25:90:03:EB:80
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby B. Schmitz" <[email protected]> To: "Craig J. Stacey" <[email protected]>, "Corby Schmitz" <[email protected]> Cc: "Daniel E. Olson" <[email protected]>, [email protected] Sent: Friday, May 11, 2012 2:44:54 PM Subject: Re: 221 Service Outage Saturday 5/18 10am-2pm rolling
Yes, I got confused on the dates. It is Saturday 5/19.
-- corby
On 5/11/12 2:36 PM, "Stacey, Craig J." <[email protected]> wrote:
Also, I presume you mean 5/19. -- Craig
On May 11, 2012, at 2:35 PM, Craig Stacey wrote:
Okay, cool. I see no issue with this. -- Craig
On May 11, 2012, at 2:30 PM, Corby Schmitz wrote:
60 seconds or less is the expected outage per-host.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 14:17, Craig Stacey <[email protected]> wrote:
What will the length of the outage be for each host? -- Craig
On May 11, 2012, at 1:52 PM, Corby Schmitz wrote:
We are replacing the 4k and its oversubscribed hardware to line rate fex shelves and the new 7K in 221.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 13:45, Dan Olson <[email protected]> wrote:
I don't think there is much that we can do, we're going to have to take this outage. Is the 4k going to reboot, or is it something upstream that is being worked on?
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby Schmitz" <[email protected]> To: [email protected] Sent: Friday, May 11, 2012 1:40:35 PM Subject: 221 Service Outage Saturday 5/18 10am-2pm rolling
We will be replacing network hardware, which will affect the server infrastructure MCS has in 221 on Saturday 5/18 between 10am and 2pm. What needs to be done ahead of time to prepare for this?
Corby Schmitz Sent from my mobile office
Dan, I'm done moving the CIS equipment, I'm going to start on the MCS stuff. I'll let you know when I'm done so you can verify connectivity. Brandon On 5/14/12 10:08 AM, "Siegel, Brandon L." <[email protected]> wrote:
Dan,
I've got the ports for your load balancers marked and will save those for last, I should be ready to move them around 11:00 on Saturday. We could also move them before Saturday if you wanted, the new equipment is already in place and ready to go.
Brandon
-- Brandon Siegel Jr. Network Engineer Computing and Information Systems Argonne National Laboratory [email protected] (630)252-0261
On 5/11/12 6:00 PM, "Schmitz, Corby B." <[email protected]> wrote:
i am copying the engineer leading the work so he can make arrangements.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 14:51, "Dan Olson" <[email protected]> wrote:
I'll also be onsite doing other work that day, so I can help troubleshoot issues if they arise. I would like to do the load balancers two connections last. 6 net load balancer address is 00:25:90:03:EB:81 15 net load balancer address is 00:25:90:03:EB:80
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby B. Schmitz" <[email protected]> To: "Craig J. Stacey" <[email protected]>, "Corby Schmitz" <[email protected]> Cc: "Daniel E. Olson" <[email protected]>, [email protected] Sent: Friday, May 11, 2012 2:44:54 PM Subject: Re: 221 Service Outage Saturday 5/18 10am-2pm rolling
Yes, I got confused on the dates. It is Saturday 5/19.
-- corby
On 5/11/12 2:36 PM, "Stacey, Craig J." <[email protected]> wrote:
Also, I presume you mean 5/19. -- Craig
On May 11, 2012, at 2:35 PM, Craig Stacey wrote:
Okay, cool. I see no issue with this. -- Craig
On May 11, 2012, at 2:30 PM, Corby Schmitz wrote:
60 seconds or less is the expected outage per-host.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 14:17, Craig Stacey <[email protected]> wrote:
What will the length of the outage be for each host? -- Craig
On May 11, 2012, at 1:52 PM, Corby Schmitz wrote:
We are replacing the 4k and its oversubscribed hardware to line rate fex shelves and the new 7K in 221.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 13:45, Dan Olson <[email protected]> wrote:
I don't think there is much that we can do, we're going to have to take this outage. Is the 4k going to reboot, or is it something upstream that is being worked on?
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby Schmitz" <[email protected]> To: [email protected] Sent: Friday, May 11, 2012 1:40:35 PM Subject: 221 Service Outage Saturday 5/18 10am-2pm rolling
We will be replacing network hardware, which will affect the server infrastructure MCS has in 221 on Saturday 5/18 between 10am and 2pm. What needs to be done ahead of time to prepare for this?
Corby Schmitz Sent from my mobile office
All the MCS drops have been moved to the new equipment. Go ahead and verify your systems, let me know if you have any issues and I can assist in the troubleshooting. Thanks, Brandon On 5/19/12 12:24 PM, "Siegel, Brandon L." <[email protected]> wrote:
Dan,
I'm done moving the CIS equipment, I'm going to start on the MCS stuff. I'll let you know when I'm done so you can verify connectivity.
Brandon
On 5/14/12 10:08 AM, "Siegel, Brandon L." <[email protected]> wrote:
Dan,
I've got the ports for your load balancers marked and will save those for last, I should be ready to move them around 11:00 on Saturday. We could also move them before Saturday if you wanted, the new equipment is already in place and ready to go.
Brandon
-- Brandon Siegel Jr. Network Engineer Computing and Information Systems Argonne National Laboratory [email protected] (630)252-0261
On 5/11/12 6:00 PM, "Schmitz, Corby B." <[email protected]> wrote:
i am copying the engineer leading the work so he can make arrangements.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 14:51, "Dan Olson" <[email protected]> wrote:
I'll also be onsite doing other work that day, so I can help troubleshoot issues if they arise. I would like to do the load balancers two connections last. 6 net load balancer address is 00:25:90:03:EB:81 15 net load balancer address is 00:25:90:03:EB:80
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby B. Schmitz" <[email protected]> To: "Craig J. Stacey" <[email protected]>, "Corby Schmitz" <[email protected]> Cc: "Daniel E. Olson" <[email protected]>, [email protected] Sent: Friday, May 11, 2012 2:44:54 PM Subject: Re: 221 Service Outage Saturday 5/18 10am-2pm rolling
Yes, I got confused on the dates. It is Saturday 5/19.
-- corby
On 5/11/12 2:36 PM, "Stacey, Craig J." <[email protected]> wrote:
Also, I presume you mean 5/19. -- Craig
On May 11, 2012, at 2:35 PM, Craig Stacey wrote:
Okay, cool. I see no issue with this. -- Craig
On May 11, 2012, at 2:30 PM, Corby Schmitz wrote:
60 seconds or less is the expected outage per-host.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 14:17, Craig Stacey <[email protected]> wrote:
What will the length of the outage be for each host? -- Craig
On May 11, 2012, at 1:52 PM, Corby Schmitz wrote:
We are replacing the 4k and its oversubscribed hardware to line rate fex shelves and the new 7K in 221.
Corby Schmitz Sent from my mobile office
On May 11, 2012, at 13:45, Dan Olson <[email protected]> wrote:
I don't think there is much that we can do, we're going to have to take this outage. Is the 4k going to reboot, or is it something upstream that is being worked on?
---- Daniel Murphy-Olson Systems Administrator Mathematics & Computer Science Division Argonne National Laboratory 630-252-0055
----- Original Message ----- From: "Corby Schmitz" <[email protected]> To: [email protected] Sent: Friday, May 11, 2012 1:40:35 PM Subject: 221 Service Outage Saturday 5/18 10am-2pm rolling
We will be replacing network hardware, which will affect the server infrastructure MCS has in 221 on Saturday 5/18 between 10am and 2pm. What needs to be done ahead of time to prepare for this?
Corby Schmitz Sent from my mobile office
participants (5)
-
Corby Schmitz -
Craig Stacey -
Dan Olson -
Schmitz, Corby B. -
Siegel, Brandon L.