Be on the ready for an short power blip to UPS feeds at 12:30PM on
Wednesday.
==
Craig
Begin forwarded message:
> From: Craig Stacey <stace(a)mcs.anl.gov>
> Date: November 30, 2009 11:51:07 AM CST
> To: datacenter(a)mcs.anl.gov
> Subject: Re: UPS work, possible outage
>
> I've heard no objections. The work is going ahead as noted below.
>
> On Nov 24, 2009, at 3:08 PM, Craig Stacey wrote:
>
>> They want to do some work on the UPS to protect the second UPS
>> unit's batteries from degrading due to low load.
>>
>> Ostensibly, this would should not affect the power to the Core, but
>> we want to be ready and choose a good time for it in case there's
>> another power blip.
>>
>> Does anyone have any time when it would be worse than others to
>> lose UPS power for a moment? Otherwise, I'm going to suggest Dec 2
>> at 12:30PM.
>> ==
>> Craig
>>
>>
>>
>
> ==
> Craig
>
>
>